Mechanical

Compressed-air piping installation — Hiep Sung

Overhead compressed-air piping installation inside the Hiep Sung workshop

Information

Client
Hiep Sung Co.
Location
Hiep Sung plant
Year
2026
Scope
Install overhead compressed-air lines, supports and safe work-at-height methods
Field
Mechanical

Overview

BTH installed gas piping for Hiep Sung inside the plant, mainly overhead routes with supports and safe work-at-height methods.

The package required coordination with existing utilities and strict control when working from scaffolding/structures.

Scope

  • Route and install overhead gas lines
  • Fabricate/install supports tied to the building structure
  • Join sections, align routes and finish connections
  • Site inspection and work-area clean-up

Execution

After route survey, the crew set access, lifted pipe into position, fixed supports and completed joints. Site photos record both the line and elevated installation work.

HSE & quality

Full PPE, fall protection at height and dropped-object control. Support fixings, alignment and joint condition were checked before handover.